Drought forces livestock farmers to make tough decisions: Our model shows the impact on inequalityTom Brady risks potential NFL fine after calling out controversial officiating in Lions’ win over PackersHarry Kane wins 2026 Ballon d’Or, becomes 1st player to claim two awards in one nightOpenAI announces three big science discoveries and a new way to work with academicsSouth Africa's lion-petting industry: We spent three years investigating and here's what we foundIndore Water Supply To Be Affected In 19 Overhead Tank Zones On October 27 As Narmada Phase I And II Pumps Shut For Pipeline RepairsCentre Questions MP Police Dial-112 Response Time Of 22 Minutes, State Officials Say Current Average Is 12 MinutesHarry Kane becomes first English player to win Ballon d'Or in 25 years after Michael OwenMicrosoft offers voluntary exit packages to 60,000 eligible employees, including in IndiaInside the narcissistic brain: fMRI research sheds light on the narcissist's struggle with empathySimhastha 2028 Preparations In Ujjain Divisional Commissioner Orders Faster Work On 19.8-Km Bypass And 98.7-Km Greenfield Road, Strict Quality ChecksBallon d’Or 2026: Full list of winners from 1956 to 2025; Harry Kane, Mbappe among contenders for 2026
NationalUpdated 1 hr ago

Indore-Dahod Rail Project Sees Successful Track And OHE Testing In 3-Km Tihi Tunnel, CRS Inspection Likely In Early November

Image: Free Press Journal

Indore (Madhya Pradesh): The wait for rail connectivity in Dhar district is nearing an end. Ahead of the inspection of the Tehi-Dhar section by the Commissioner of Railway Safety (CRS), the construction department of Railways successfully tested the 3 km-long track laid in Tehi tunnel and the 2 km-long overhead equipment (OHE) of the electrical line using a wagon on Monday.

The long-awaited Indore-Dahod rail connectivity project is moving rapidly towards realisation. A successful trial run of a railway wagon (engine) was conducted between Pithampur and Tihi in Dhar district. This has strengthened prospects of commencing passenger train services on the route soon.

A senior railway official confirmed the development on Monday. He said a tower wagon entered the tunnel from the Tihi side and exited towards Pithampur. The tower wagon became the first train to safely pass through the Tihi-Pithampur tunnel.

Chief engineer of Western Railway Dheeraj Kumar and deputy chief engineer Dheeraj Kumar were present during the trial. Sources said the successful test has paved the way for CRS inspection, likely in the first week of November.

MP Shankar Lalwani said Railways was working to complete the project quickly. Operations on the section are expected to begin after the Commissioner of Railway Safety conducts the scheduled inspection.

The Indore-Dahod rail line is significant for improving connectivity across Malwa and Tribal regions. It is expected to provide Dhar and surrounding areas with better rail access to Indore, while benefiting industrial activities, trade and public movement.

The successful engine trial between Pithampur and Tihi marks a significant milestone. Once the CRS inspection is completed and necessary formalities are fulfilled, the section will be cleared for rail operations

Indore Central Museum To Remain Closed For Nearly Five Months From October 26; ₹11.75 Crore Renovation To Add Modern Galleries, Visitor Facilities

This content is published by Free Press Journal and has not been created or edited by Hello Headlines. View original

More in National

See all