New study uses 3-30-300 rule to evaluate urban greenness in five major Canadian cities, finds room for improvementNvidia reinstates Jensen Huang as CEO, board director with immediate effectJensen Huang returns as Nvidia CEO after board reinstates him following investigationBRS responsible for debt, BJP for destabilising India: BhattiWATCH: Sufyan Moqim Accuses Harshit Rana Of 'Abusing' Pakistan Batters In IND vs PAK ClashZverev defends No. 1 ranking after ATP Finals loss to AlcarazJensen Huang is back as Nvidia’s CEODelhi: Man Attacks Policemen With Knife At Jama Masjid Police Station, 9 InjuredHow a Hyderabad Doctor Helped Bring the Cost of a Rs 9-Crore Drug Down to Rs 2.5 LakhBlade Runner 2099 is an inventive twist on a cyberpunk classic10 months after final chaos, AFCON title winner to be decided by CAS rulingSangareddy: 120 kilos of soya crop gutted in fire
NationalUpdated 19 min ago

Palghar: Virar Sports Complex Cost Rises By ₹25 Crore To ₹68 Crore, Facility Remains Incomplete After Inauguration

Image: Free Press Journal

Vasai, November 23, 2026: Signs of a fresh political clash are emerging in the city over the naming of the much-discussed sports complex at Bolinj in Virar West, a project of the Vasai-Virar City Municipal Corporation (VVCMC) that has been stalled for eight years.

While various sports organisations have demanded that the complex be named after former MLA Hitendra Thakur, BJP Leader of the Opposition Manoj Patil has submitted a representation to the Mayor demanding that it be named after ‘Narveer Chimaji Appa’.

This modern sports complex has been built on the MHADA ground in Virar West. Even though work on the complex was incomplete, it was hastily inaugurated on October 3, 2026. That move had already sparked a fierce political confrontation between the Bahujan Vikas Aghadi (BVA) and the BJP.

Naming Dispute Sparks Political Tensions

Deciding whose name to give the complex has now become a matter of political prestige. On one side, sports bodies are pressing for Hitendra Thakur’s name, while on the other, the BJP has pushed forward a proposal in the name of Narveer Chimaji Appa.

Political circles anticipate that the atmosphere will heat up considerably if the naming proposal comes up for discussion at the general body meeting.

Even though a month and a half has passed since the inauguration, most of the work on the complex remains unfinished. Additionally, the tendering process to hand over operations of the complex to a private body, along with other administrative tasks, is pending at the municipal corporation level. Because of this, frustrated citizens are now asking when the sports complex will actually open for athletes, rather than focusing on the naming dispute.

Project Cost Rises From Rs 43 Crore To Rs 68 Crore

Because local athletes had to rely on grounds in Mumbai for practice, there had been a demand for years to build a well-equipped sports complex in Vasai-Virar.

Accordingly, the municipal corporation held the groundbreaking ceremony in November 2017 and awarded the Rs 43 crore contract in 2018 to a company named ‘N. A. Construction’.

Also Watch:

Vasai-Virar Mayor Ajiv Patil Accuses Opposition Of Misleading CM Over Bolinj Sports Complex Inauguration | VIDEO

However, due to administrative delays over eight years, the project's cost has jumped directly from Rs 43 crore to Rs 68 crore. The municipal corporation claims the cost increased due to changes in the building’s interior layout and because of GST. It has also stated that the remaining works will be completed in phases.

To get details on exclusive and budget-friendly property deals in Mumbai & surrounding regions, do visit: https://budgetproperties.in/

This content is published by Free Press Journal and has not been created or edited by Hello Headlines. View original

More in National

See all