PM Modi: India has shown it can break limits and unlock possibilitiesLicences of Matam Al Yamani, Madhapur Bawarchi halted over food hygieneGautam Gambhir's dugout head massage goes viral amid India vs New Zealand seriesINS Sahyadri arrives in Vietnam for three-day goodwill visitTransport sector outlook: Weak rail container volumes, subdued air traffic to weigh, JM Financial saysIndia rising in global manufacturing, but skilled workforce remains a challengeUP Politics: Akhilesh Yadav vs Dhirendra Shastri Over Kunda Ram Katha, BJP Leaders Join the RowToyota Innova Hycross Facelift To Launch This Week – All Key DetailsH-1B visa delays and Trump's rules force tech workers to leave USUP Politics: SP Links PDA With Lord Ram, Krishna and Shiva in New Poster, Counters BJP's Hindutva NarrativeIPL 2027: 3 CSK players who should not have been retainedNFR Undertakes Infrastructure Up-gradation to Boost Safety and Efficiency
NationalUpdated 18 min ago

NFR Undertakes Infrastructure Up-gradation to Boost Safety and Efficiency

Image: Free Press Journal

Northeast Frontier Railway (NFR) remains committed to strengthening the safety and reliability of train operations through regular infrastructure monitoring, timely maintenance and continuous technological upgradation. The adoption of modern, technology-driven systems and advanced maintenance practices is a key priority for ensuring safe, smooth and efficient train movement across the zone. By focusing on critical locations and undertaking proactive maintenance measures, NFR is further enhancing operational safety, reducing potential risks and ensuring greater reliability of railway infrastructure.

During October 2026, NFR has undertaken several significant initiatives in the signalling and safety domain. Thick Web Switch Point machines with clamp type locking have been installed at six stations each across Katihar & Lumding division, four stations each across Alipurduar & Rangiya division and three stations across Tinsukia disvision. System Integrity Testing has been carried out at seven stations across Katihar, Rangiya and Lumding divisions, while an extensive System Integrity Testing drive covering 40 Level Crossing gates has also been completed across all divisions.

Further strengthening signalling infrastructure and enhancing safety at level crossings, 04 sliding booms have been commissioned at various level crossing gates across Lumding, Alipurduar and Rangiya Divisions. Additionally, Tamping Machines attended to 835.85 Track Kilometres (Tkm) during October 2026, taking the cumulative progress to 6,606.85 Tkm.

During October 2026, Tamping Machines attended to a total of 376 Points & Crossings, taking the cumulative progress to 2,670 Nos. In the area of track safety and maintenance, 2,426.97 Track Kilometres (Tkm) of track were tested through Ultrasonic Flaw Detection (USFD), bringing the cumulative progress to 15,881.57 Tkm. Additionally, 824 Flash Butt (FB) welds were tested using Phased Array Ultrasonic Testing (PAUT) technology during the month, taking the cumulative total to 12,585 FB welds.

These infrastructural upgrades play a crucial role in ensuring safe train operations, improving reliability and enhancing the overall capacity of railway operations. NFR remains committed towards providing a safer, more efficient and punctual travel experience for its passengers through continuous monitoring and strengthening of its infrastructure.