Hyderabad streetlights: New agency, but relief only by January

Hyderabad: The Greater Hyderabad Municipal Corporation (GHMC) Standing Committee has approved a Rs 1,720.83-crore, 10-year contract with a private joint venture to maintain about 7.60 lakh LED streetlights across Hyderabad’s three municipal corporations. Meanwhile, residents are filing up to 200 complaints a day about faulty lights.
The contract has gone to a joint venture of BAC Infratech Pvt Ltd and Vinci Global Pvt Ltd. It covers operation and maintenance of the streetlights, the Centralised Control and Monitoring System (CCMS) panels and related infrastructure in the GHMC, the Cyberabad Municipal Corporation (CMC) and the Malkajgiri Municipal Corporation (MMC).
The GHMC, the nodal agency for the Core Urban Region (CURE), has already issued a Letter of Agreement to the joint venture, officials told Telangana Today. However, the formal agreement is yet to be signed.
Lights, costs shared
Of the 7.60 lakh lights, 3,30,487 are in the GHMC, 1,85,258 in Cyberabad and 2,44,846 in Malkajgiri.
The cost will be shared on the basis of the number of lights. The GHMC will bear Rs 747.72 crore, Cyberabad Rs 419.16 crore and Malkajgiri Rs 553.95 crore.
The joint venture was the lowest bidder, quoting Rs 153.60 per streetlight a month, according to the government order approving the project. The administrative sanction was earlier Rs 1,341.60 crore. Osmania University will act as the third-party monitoring agency, reports said.
150-200 complaints a day
The three corporations receive 150 to 200 complaints a day about faulty streetlights, officials told The New Indian Express. With no regular maintenance agency in place, some complaints take days or even weeks to resolve, and faulty CCMS panels have made matters worse.
Since the earlier contract ended, the civic bodies have relied on temporary staff and private subcontractors, but this has not been enough.
Officials cited an acute shortage of field engineers, no clear record of the staff deployed and a freeze on buying new materials. Maintenance engineers are also handling other electrical work, leaving them little time to supervise repairs.
Relief only by January
Personnel and equipment are yet to be deployed. Administrative delays, including the absence of a regular chief engineer, who is on leave, have slowed the process, officials said.
Mobilisation is expected to take another month or two, with full-scale operations likely to begin only by January 2027. Until then, residents may have to put up with dark stretches and delayed repairs.
Energy Efficiency Services Ltd (EESL), a joint venture under the Union Power Ministry, maintained about 5.4 lakh LED streetlights in the erstwhile GHMC area under a contract signed in 2017. That contract expired on April 30, 2025.
The two sides have long been at odds over unpaid dues. In October 2024, EESL said the GHMC owed it Rs 144.48 crore, besides annuity payments of Rs 57.10 crore for six months.
According to the GHMC, more than 70 per cent of the city’s LED fixtures have outlived their lifespan because dues to EESL were not paid. This has led to lights blinking, staying on during the day, and whole stretches going dark.